These suggested installation guidelines represent generally accepted procedures for successful installation of Kinetics Noise Control ICW Ceiling Hanger for ceiling system isolation. These suggestions may be followed, modified, or rejected by the owner, engineer, contractor, and/or their respective representative(s) since they, not Kinetics Noise Control, are responsible for planning and executing procedures appropriate to a specific application. Kinetics Noise Control reserves the right to alter these suggestions and encourages contact with the factory or its representatives to review any possible modification to these suggested guidelines prior to commencing installation.

  • 1. Installation of an isolated ceiling system that uses Kinetics Noise Control ICW Wood-Frame Ceiling Hangers requires following materials (as specified by others and purchased separately):
    • 1-1/2" x 1/2", 16-gauge cold-rolled channel.
    • 7/8" 20- to 25-gauge drywall furring channel.
    • Anchors for mounting into non-isolated wood-frame construction (e.g., joists, trusses).
    • 1/2" or 5/8" thick gypsum board (Type X).
    • Appropriate tools and equipment for installation.

    If submittal drawings have been prepared for the installation, review drawings for completeness and accuracy; otherwise, refer to Selection Guidelines for selecting ceiling hangers.

  • 2. When ceiling height is to be maximized, it is important to be aware of which direction the joists supporting the structural floor above run. The grid must be oriented so that the cold-rolled steel channel member that is supported directly by the isolators runs parallel to these. Please note this can affect the basic arrangement of the isolators and thus their size and quantity. Mark grid pattern using the following criteria:
    • Isolators installed at the perimeter must be located not more than 12" from the edge of the isolated ceiling; maintain at least a three-inch clearance from the perimeter.
    • Isolators may be located up to 48" along the perimeter of the isolated ceiling.
    • Isolators mounted mid-room (i.e., those isolators not at the perimeter) may be located up to 48" on center each way (o.c.e.w.); mid-room isolators should be spaced evenly in each direction.

    Submittal drawings, if provided, override general location guidelines provided above.

  • 3. Remove ICW Hangers from box. Confirm capacity of each isolator to ensure proper location in grid. If provided, shop drawings will identify location of specific hanger by capacity rating. After determining the direction the cold-roll channel will run (orientation is not important acoustically; refer to Step 2), locate the isolators on the grid. Anchor isolators to joists using appropriate fastener through the opening(s) on the hanger bracket. Slide cold-rolled channel through the channel clip on the leveling bolt. Position the cold-rolled channel to prevent contact at partition/wall/column or any other non-isolated structural component. Inter-connect ends of cold-rolled channel using appropriate practices for ceiling grid installation.
  • 4. Attach drywall furring channel to cold-rolled steel and inter-connect the ends of the furring channel using appropriate practices for ceiling grid installation. Furring channel cannot contact non-isolated structural components.
  • 5. After assembling the ceiling grid, check for levelness. By loosening or tightening the bottom nut of the leveling bolt/channel clip, the grid can be adjusted to level. Do not overly loosen. A minimum 1/4" of threaded rod should be exposed above the threaded spring cap.
  • 6. Install CPT perimeter interface at partitions/walls, columns, and around any non-isolated building components to create a 3/8" wide resilient layer that ensures the isolated ceiling remains decoupled from the non-isolated structure. As the gypsum board is attached to the grid, the springs will compress (1/2" to 1-1/4" nominally depending on spring capacity) allowing the ceiling system to lower into final position. Position the CPT to account for this change to final elevation. Trimming the CPT may be required following installation of the gypsum board. If an alternate method for ensuring that the isolated ceiling remains decoupled is employed (e.g., using resilient backer rod), be sure to maintain a 3/8" gap from non-isolated structural components.
  • 7. Install the gypsum board using accepted practices for attaching to the grid system. Be certain to maintain a 3/8" gap between non-isolated structural components and the isolated ceiling to ensure that the gypsum board does not contact any non-isolated structural components. Do not allow gypsum board to rest on top edge of CPT; it should abut the perimeter isolation board. Do not allow the CPT to become compressed against the non-isolated structure. In some cases, additional adjustment of the gypsum board may be necessary to achieve levelness, consult factory for procedures.
  • 8. Trim CPT as required and caulk gap using a resilient, non-hardening caulk.